Blog / Missing Middle Housing
Toronto As-of-Right Permit Timeline: How Long a Multiplex Permit Takes
Written by Anthony Palleschi · November 29, 2026 · 9 min read

The Ontario Building Code gives a municipality 10 business days to review an application for a house. On paper, a Toronto multiplex permit should take two weeks. In practice, it takes most builders 6 to 10 months. Not because Toronto is slow. Because a multiplex application is reviewed by four City divisions at once, and the 10-day clock is only one of them.
I'm Anthony Palleschi, a real estate sales representative in Toronto, working with owners and builders on sites where the permit timeline is part of the lot value. This post sets out where the time goes, the four review streams, and what an owner can do before listing to shorten a builder's path.
The four review streams
A Toronto multiplex building permit application lands at Toronto Building, but the review is not a single-office review. Four divisions look at the application in parallel, each with its own checklist and its own comment letter.
| Division | What it checks | Typical timeline |
|---|---|---|
| Toronto Building | Zoning compliance, Ontario Building Code, structure, plumbing, mechanical | 2 to 4 months |
| Urban Forestry | Private tree permit, Tree Protection Plan, boulevard trees | 3 to 8 weeks |
| Toronto Water | Water meter, service upgrade, storm water management | 4 to 12 weeks |
| Transportation Services | Driveway width, curb cut, boulevard works, on-street parking | 4 to 10 weeks |
The permit is issued only when all four reviews are cleared. Every review can issue comments, and every round of comments sends the file back for a revised drawing set.
Where the time goes
A clean first submission on an as-of-right fourplex typically moves this way:
- Weeks 0 to 2: Toronto Building confirms the application is complete and opens the file.
- Weeks 2 to 6: first round of review comments from all four divisions.
- Weeks 6 to 10: architect and consultants prepare a revised drawing set.
- Weeks 10 to 14: second review round.
- Weeks 14 to 18: a second revision, if needed.
- Weeks 18 to 22: final clearances.
- Weeks 22 to 26: permit issued.
A messy submission, with zoning assumptions the examiner does not accept, often needs three or four revision rounds. The timeline stretches to 40 weeks, or nearly 10 months.
A rezoning or a minor variance adds a further block of time on the front end. See my posts on the minor variance process and timeline and severance and minor variance at the Committee of Adjustment.
Why a multiplex is not caught by the 10-day rule
Section 8 of the Ontario Building Code sets a 10 business day limit for a House-stream application. A multiplex of six or ten homes is still inside the House stream when the City treats it as a residential building of three storeys or fewer. But the 10 days start only when Toronto Building accepts the application as complete, and the clock pauses as soon as a comment letter is issued.
Three reasons the 10 days rarely apply in practice:
- The three other divisions (Urban Forestry, Toronto Water, Transportation Services) have separate review windows that are not bound by the 10 days.
- A comment letter from Toronto Building on the first round resets the clock to zero when the revised drawings are submitted.
- A zoning examiner's dispute with the applicant on how a rule applies can be referred to the Zoning Review Services team, which has its own queue.
The 10-day rule is enforced on a simple house addition. A multiplex is rarely that simple.
Before Bill 23: site plan control
Until Ontario's Bill 23, More Homes Built Faster Act, 2022, a Toronto multiplex typically went through site plan control as well. Bill 23 removed site plan control for residential projects of 10 or fewer units. For most Missing Middle projects, the removal takes a 6 to 12 month step off the timeline.
A project of 11 or more units still goes through site plan review. A project of 10 or fewer units in a site plan control area with complex servicing is sometimes asked to file a limited site plan agreement. For the small builder, the Bill 23 change is one of the main reasons a fourplex is viable today.
The pre-application meeting
Toronto Building offers a free pre-application meeting with a permit examiner. It is one hour, the applicant brings draft drawings, and the examiner reads them against the by-law and the Code. The output is a letter of issues to fix before the formal application.
In the files I have seen, a pre-application meeting cuts one round of review comments from the formal application. On a timeline where each round is 3 to 6 weeks, the saving is real. The meeting is booked through the City's Development Review system, usually 2 to 3 weeks out.
For a lot that will go on the market with a conceptual design, the pre-application meeting is a seller's asset. The seller walks away with a one-page letter from the City that says what a builder can and cannot do. That letter is worth more than most of the broker commentary that usually accompanies a listing.
What the Urban Forestry review adds
Urban Forestry reviews the tree permit and the Tree Protection Plan. The review is on a separate track from Toronto Building, and the private tree permit is a precondition of the building permit.
An arborist report submitted with the first application saves the delay. An arborist report submitted after the first comment letter adds 4 to 8 weeks. See my private tree by-law post for how the by-law works.
A boulevard tree in front of the lot is a separate review under Chapter 658. A driveway cut, a new sewer connection, or a utility service line that affects a boulevard tree's roots triggers the second review.
What the Toronto Water review adds
Toronto Water looks at three things on a multiplex application:
- The water meter. A multiplex of four to ten units often needs a larger water service than the existing house has. The service upgrade is a separate application and a separate charge.
- The sanitary service. The existing sanitary connection may be at the end of its life. A new connection is often required.
- Storm water management. A multiplex adds impervious surface, which has to be managed on site. Smaller projects use a flow control device. Larger projects use a cistern or an infiltration bed.
The Toronto Water review is the one that most often brings surprises. A service upgrade from a 15-millimetre to a 25-millimetre water line can require the City to open the road, which is a Transportation Services permit and a schedule in itself.
What the Transportation Services review adds
A new driveway, a new curb cut, a change to the on-street parking plan and any construction equipment staging in the right of way are all Transportation Services reviews. The division's permits for work in the City's road allowance run on their own timeline and are usually straightforward for an as-of-right multiplex.
The exception is a lot that needs a widened driveway or a new curb cut on a major street. See my post on Toronto major streets zoning for how major street rules interact.
What an owner can do before listing
Three steps reduce a builder's timeline risk, and therefore raise what a builder can pay.
- Order a zoning review summary from the City. A $400 Zoning Preliminary Review (ZPR) sets out the zoning rules for the lot in writing. A builder reading a listing with a ZPR in hand knows the zoning is settled.
- Book the free pre-application meeting. Even without a formal design, an examiner's one-page letter is a selling tool.
- Order an arborist report. The 2 to 3 page report costs $1,000 to $2,500 and answers the single most common Urban Forestry question before the application.
For the pricing framework a builder uses, see how builders price land in Toronto. For the questions a builder asks a seller, see selling an estate property to a builder in Toronto.
Common mistakes
- Treating the 10-day rule as the timeline. The 10 days is one of four parallel reviews. A permit that comes in two weeks is a story, not a plan.
- Submitting without the tree report. Urban Forestry stops the whole file until the report is in.
- Underestimating the water service. A multiplex often needs a bigger water line. A late application for the service upgrade adds 2 to 3 months.
- Skipping the pre-application meeting. One hour of the examiner's time saves one round of comments on the permit.
- Assuming the zoning examiner will agree with the architect. Where the by-law wording is unclear, the examiner's reading is the operative one. The disagreement is worked out in writing, not in the design.
Questions to ask about your timeline
- Is the project fully as-of-right, or does it need a variance?
- Has a Zoning Preliminary Review been ordered on the lot?
- Have you booked a pre-application meeting at Toronto Building?
- Has an arborist walked the lot?
- Has a servicing engineer checked the water and sanitary capacity?
If you want to walk through a realistic timeline for a specific lot, see how I work with sellers and builders, or reach me through the contact page.
Planning and development potential is property-specific and subject to zoning, approvals, site conditions, municipal review and other due diligence.
Sources
All pages opened on November 25, 2026 (PT).
- Government of Ontario, Ontario Building Code, O. Reg. 332/12: section 8, the 10 business day review window for a House-stream application.
- Government of Ontario, Bill 23, More Homes Built Faster Act, 2022: the removal of site plan control for residential projects of 10 or fewer units.
- City of Toronto, Building Permits: the application process, fees and timelines.
- City of Toronto, Zoning Preliminary Review: the formal zoning read for a specific lot.
- City of Toronto, Toronto Water, Water Service Applications: the service upgrade process and the storm water management requirements.
Frequently asked questions
How long does a Toronto multiplex building permit take?
An as-of-right multiplex permit takes most builders 6 to 10 months from the first drawings to the permit in hand. The Ontario Building Code deadline for a complete House-stream application is 10 business days, but a Toronto multiplex is almost never caught up in a single 10-day review. The real timeline reflects zoning review, Urban Forestry review, Toronto Water review, and one or two rounds of comments.
What is an as-of-right permit in Toronto?
An as-of-right permit is a building permit for a project that complies with the zoning by-law without a variance or a rezoning. The application goes through Toronto Building's standard permit review, with no hearing at the Committee of Adjustment and no Council vote. The 6 to 10 month timeline is for this kind of permit.
How long does a Committee of Adjustment decision add?
A minor variance adds about 3 to 5 months to the building permit timeline. The Committee of Adjustment hearing is usually 60 to 90 days after a complete application, and the decision is final about 20 days after the hearing unless appealed. A rezoning application adds 12 to 24 months on top of the base permit timeline.
What is the 10 business day rule for Toronto building permits?
Under section 8 of the Ontario Building Code, a municipality has 10 business days to review a House-stream application and either issue the permit or issue a notice listing the Code issues. The 10 days start only after Toronto Building has accepted the application as complete. A multiplex application that comes back with a list of zoning or utility issues resets the clock when the applicant submits a revised drawing set.
What are the review streams for a Toronto multiplex permit?
A multiplex application goes through four main reviews in parallel: Toronto Building (zoning, Building Code, structural, plumbing), Urban Forestry (private tree permit, Tree Protection Plan, boulevard trees), Toronto Water (water meter, service upgrade, storm water management), and Transportation Services (driveway, curb cut, boulevard works). Each review can issue its own comments, and the permit is issued when all four are cleared.
Can I speed up a Toronto multiplex permit?
The two biggest time savers are a complete application on the first submission and a pre-application meeting with Toronto Building. A pre-application meeting is free, takes about an hour, and often catches the zoning questions that would otherwise show up in the first round of comments. A thorough arborist report submitted with the application avoids the Urban Forestry delay.
What is a pre-application meeting at Toronto Building?
A pre-application meeting is a free consultation with a Toronto Building examiner about a specific project. The applicant brings a draft site plan and a draft set of elevation drawings. The examiner reads them against the zoning by-law and the Building Code and lists the issues to fix before submission. Most pre-application meetings save one round of review comments on the formal application.
Does a Toronto multiplex need a site plan application?
No, in most cases. Ontario's Bill 23 removed site plan control for residential projects of 10 or fewer units. A fourplex, sixplex, eight or ten unit project no longer goes through site plan review. Projects of 11 units or more do, and in some cases a project of 10 or fewer units with design or servicing complexity is still asked to file.