Building permits for a Toronto multiplex: the zoning certificate, the application, review times and inspections

This guide is for small builders and owners who plan a multiplex, a conversion or a suite in Toronto and want to know how the building permit works. It covers the Zoning Applicable Law Certificate that makes an application complete, the drawings and forms Toronto Building asks for, the House, Small Building and Large and Complex review streams with their time limits, the City's free pre-approved fourplex and sixplex plans, how examiners' notices work, and the inspections that close a permit. Every fact comes from a City of Toronto page read on November 17, 2026.

Written by · Updated November 17, 2026 · 11 min read

Key takeaways

  • Toronto Building treats an application as complete only when it includes an issued Zoning Applicable Law Certificate, and there is no time frame for reviewing an incomplete one.
  • Complete applications are reviewed within 10 business days in the House stream, 15 in the Small Building stream, and 20 or 30 in the Large and Complex stream.
  • The House stream covers a detached, semi-detached or row house with no more than two units, plus garden and laneway suites. Other Part 9 buildings go to the Small Building stream.
  • A Zoning Applicable Law Certificate for a new house of up to two units, or a conversion of a house, costs $644.38 from January 1, 2026, and its fee is credited to the permit.
  • The City offers free pre-approved plans for four-unit and six-unit multiplexes, but a qualified design professional must still complete and seal the site-specific parts.
  • Inspections cover footings, foundations, framing, fire separations, insulation, plumbing, HVAC and the finished building. The owner books a final inspection to close the permit.

Where the permit fits in a multiplex project

A multiplex that fits the zoning needs no rezoning and no Committee of Adjustment hearing. It still needs a building permit, which has its own steps, forms and time limits.

I am Anthony Palleschi, a real estate sales representative with Weiss Realty Ltd., Brokerage. This guide sets out Toronto Building's steps in order, with the time limits and fees the City publishes. It follows the guides on multiplex zoning, screening a lot and development charges and fees, which covers the permit fee and when charges are paid.

Step 1: the Zoning Applicable Law Certificate

Toronto Building's review time limits apply only to complete applications. The City's review streams page, modified June 26, 2026, lists what makes an application complete:

  • The application form is filled in and signed by the owner or the owner's authorized agent.
  • One set of plans and specifications is attached.
  • An issued Zoning Applicable Law Certificate is included, with confirmation that every applicable law it lists has been satisfied.
  • All fees are paid.

The page adds that applications with no certificate are incomplete, and that there is no time frame for reviewing an incomplete application.

The Zoning Applicable Law Certificate is a detailed review of the plans for zoning and for other applicable law, done before the permit application. The City's page, modified October 15, 2026, says one certificate application includes up to three reviews. It needs a site plan based on a current survey by an Ontario Land Surveyor, with setbacks, a zoning summary and grade elevations, plus floor plans, elevations and cross sections.

Zoning Applicable Law Certificate fees, effective January 1, 2026, non-refundable, from the City of Toronto's page modified October 15, 2026, read November 17, 2026
Type of applicationFee
New laneway or garden suite$644.38
New house of up to two units, or additions, conversions and alterations to a house$644.38
New building, addition or alteration other than a house, up to 300 square metres$888.14
New building, addition or alteration other than a house, over 300 square metres$1,863.82
Garages, porches, balconies and similar accessory structures$214.79
Other proposals, such as driveway widening or landscaping$214.79

When the permit application is filed with the City's declaration form for the certificate, the certificate fee is credited against the permit fee. The page also mentions a voluntary AI-assisted pre-check that flags possible problems before an application is submitted.

"Applicable law" means the other laws the zoning examiner checks before a permit can issue. The City's plan review page names the Conservation Authorities Act, the Planning Act, the Environmental Protection Act and the Ontario Heritage Act. A lot in a ravine area, a heritage district or a contaminated site needs those approvals first. The trees and ravines guide covers the most common one on house lots.

Step 2: the review streams and their time limits

Toronto Building sorts applications into streams by building type:

Toronto Building review streams for complete applications, from the City of Toronto's page modified June 26, 2026, read November 17, 2026
StreamWhat it coversReview time for a complete application
HouseDetached house, semi-detached house or row house with no more than two units, plus garden and laneway suites10 business days
Small BuildingBuildings within Part 9 of the Ontario Building Code, other than houses15 business days
Large and Complex BuildingBuildings within Part 3 of the Ontario Building Code20 business days for large buildings, 30 for complex buildings
Express ServicesListed small projects, including conversions to no more than two unitsGoal of 3 business days after intake

Part 9 of the Ontario Building Code covers houses and small buildings, and Part 3 covers larger ones. A duplex in a house goes to the House stream. A triplex, fourplex or sixplex goes to the Small Building stream if it falls within Part 9, or to the Large and Complex stream if it falls within Part 3. The designer confirms which part applies.

The same page describes reliance on a professional engineer's seal. As expanded on July 14, 2025, where the drawings for a new house or a material alteration to a house carry an engineer's seal, Toronto Building does an expedited review and relies on the seal for the matters it covers. The engineer lists those matters on the Assumption of Responsibility for Engineering Content Form.

Step 3: the drawings and forms

The City's multiplex conversion guide, modified July 14, 2026, covers turning an existing house into a duplex, triplex, fourplex, fiveplex or sixplex. It asks for drawings on standard sheets, to scale, fully dimensioned, signed and dated, all in PDF form:

  • A site plan tied to a current survey, with property lines, existing and proposed buildings, setbacks, a summary of the permitted and proposed zoning figures, grade elevations, parking, driveways, landscaping and accessory structures.
  • Floor plans for every level, showing existing and proposed uses, smoke alarms, carbon monoxide detectors and plumbing fixtures, with the existing and new construction.
  • Cross sections with every floor, wall and roof assembly, footing and foundation details, floor to ceiling heights and stair details.
  • Construction details and notes, including guards and their connections.

A drawing by a qualified designer must carry the designer's name, registration number, qualification number, signature and stamp. The forms the guide lists are:

  • The Application to Construct or Demolish, for every submission.
  • Schedule 1, Designer Information, for designers other than engineers and architects.
  • The Assumption of Responsibility for Engineering Content Form, for a duplex with engineer-sealed drawings.
  • The Rental Renovation Licence Screening Form, for any permit to repair or renovate a home, to show whether the work also needs a licence under Municipal Code Chapter 662.
  • For an addition: a Municipal Road Damage Deposit for exterior work, a Residential Infill Public Declaration Notice where the additions total 100 square metres or more, and a Tree Declaration Form where private or City trees could be damaged.

Mechanical, plumbing and drain permits can follow the building permit application online. A plumbing data sheet goes in with the building application. For one-unit and two-unit houses no plumbing plans are needed unless there is a reverse-sloping driveway. All other residential plumbing applications need drawings of each floor.

The conversion guide lists the fees effective January 1, 2026, including $56.33 for each new residential unit, and points to the City's permit fee page for the full schedule. The guide also asks applicants to leave personal information, such as the owner's name or phone number, off the drawings, because building plans can be disclosed under the Municipal Freedom of Information and Protection of Privacy Act.

The pre-approved fourplex and sixplex plans

The City offers free pre-approved plans for four-unit and six-unit multiplexes. The page, modified November 3, 2026, says LGA Architectural Partners won the City's request for proposals to prepare them. There are narrow and wide versions of each, with electric, gas or hybrid heating for the fourplex and electric or hybrid for the sixplex.

The plans meet the Building Code and the City's zoning requirements for the building design itself. The placement on the lot is still reviewed for each site. The applicant enters the plan number on the application form instead of submitting the plan. A qualified design professional must still take responsibility for the site-specific parts in signed and sealed letters:

  • An architectural letter confirming the exposing building face diagrams and elevations, the final cladding, and for a sixplex whether window sprinklers or fire shutters are used.
  • A structural letter confirming the soil's bearing capacity, the footing depths of neighbouring buildings, any shoring and the angle of repose next to neighbouring lots. Shoring needs separate drawings.
  • A mechanical letter confirming the HVAC type, heating and cooling loads, duct runs, incoming services and sanitary connection.

The application also needs a site plan and a lot grading plan showing that the design causes no new ponding on the lot or its neighbours. Any change to the plan, including to the HVAC or plumbing, ends its pre-approved status, and the application goes through the regular process.

Step 4: examiner's notices and resubmissions

The plan review page lists the order of review: zoning, then Building Code, then mechanical plans, then fire prevention for some multi-unit buildings with fire protection systems. If the project complies, the permit issues. If not, the examiner sends a notice that explains why.

To answer a notice, upload revised drawings through the File Submission Hub as a single PDF, with revision bubbles where things changed, and send only the changed pages. Only one drawing submission is accepted at a time, and the next upload waits until the examiner accepts it. Supporting documents go to the examiner by email, with the permit number and address in the subject line. Where a design cannot meet the zoning, the page points to a minor variance from the Committee of Adjustment, after which the permit can proceed on the Committee's terms. The severance and minor variance guide explains that process.

The status of each application shows on the City's permit status site. The Missing Middle guide on looking up permits explains what each status means.

Step 5: inspections and closing the permit

The City's inspections page, modified November 29, 2024, says Subsection 1.3.5.1 of the Ontario Building Code requires the builder to notify the City when the work is ready for each mandatory inspection, and that the cost is included in the permit fee. Inspections run Monday to Friday, 8:30 a.m. to 4:30 p.m., and can be requested online from the next business day up to four weeks ahead.

For Part 9 buildings, the City's schedule for small buildings lists these building inspections and when to call:

Building inspections for Part 9 buildings and when to call, from the City of Toronto's schedule modified November 29, 2024, read November 17, 2026
InspectionWhen to call
FootingsFormwork complete, before concrete is poured
FoundationsAt completion
Structural framingAt completion, with plumbing and HVAC rough-in
Fire separationsWall, floor and shaft separations and fire stopping complete, before interior finishes
Insulation and vapour barrierComplete, before interior services are installed
Fireplaces, gas appliances and chimneysAt the start of installation
Life safety systemsStandpipe, sprinkler, fire alarm and emergency lighting complete
OccupancyConsult the inspector
Final interior and final exteriorAt completion of interior and exterior work

Plumbing has its own list: outside sewers and the water service before backfilling, inside sewers, the rough-in of supply, drains and vents, occupancy and final. HVAC has rough-in, occupancy and final inspections. Inspections take place within two business days of the date requested. The stamped permit drawings must be on site, and any part covered before it passed inspection must be uncovered.

Before anyone moves into part of an unfinished building, the building must meet Division C, Subsection 1.3.3 of the Ontario Building Code, and an Authority to Occupy application must be submitted. When the work is done, the owner books a final inspection to close the permit. The City warns that open permits may impede future real estate transactions.

What this means for a builder's schedule and an owner's sale

For a builder, the permit timeline starts with the certificate. A pro forma that assumes 15 business days for a fourplex review should also allow for the certificate's reviews, each examiner's notice and each resubmission. The guide to testing the numbers shows where carrying costs enter.

For an owner selling to a builder, the permit steps explain why a builder's offer can have a long closing or a condition tied to approvals. The guide to reading a builder's offer covers those conditions.

Questions to ask before you apply

  • Is the project a house, a Part 9 building or a Part 3 building, and which stream will review it?
  • Has a Zoning Applicable Law Certificate been issued, and does every applicable law it lists have its approval?
  • Would one of the City's pre-approved fourplex or sixplex plans fit this lot without changes?
  • Does the work need a Rental Renovation Licence, a Tree Declaration or a road damage deposit?
  • Who on the design team answers examiners' notices, and how fast?
  • Who books each inspection, and who books the final one that closes the permit?

If you are looking for a lot where a multiplex permit has a clear path, the contact page reaches me directly.

Planning and development potential is property-specific and subject to zoning, approvals, site conditions, municipal review and other due diligence. This guide is illustrative and does not guarantee similar permissions or outcomes for another property.

Frequently asked questions

How long does a Toronto building permit take for a multiplex?

Toronto Building's review streams page, modified June 26, 2026, says complete applications are reviewed within 10 business days in the House stream, 15 business days in the Small Building stream and 20 business days for large buildings or 30 for complex buildings. The clock applies only to complete applications. An application without an issued Zoning Applicable Law Certificate is incomplete and has no review time frame.

What is a Zoning Applicable Law Certificate in Toronto?

It is a preliminary review of the plans that confirms they meet the zoning by-law and other applicable law, so the building permit application can be complete. The City's page, modified October 15, 2026, says a certificate application includes up to three reviews, and that its fee is credited to the building permit fee when the permit application is made with the City's declaration form.

How much does a Zoning Applicable Law Certificate cost in Toronto?

The City's fees effective January 1, 2026 are $644.38 for a new laneway or garden suite, and $644.38 for a new house of up to two units or for additions, conversions and alterations to a house. A building other than a house costs $888.14 up to 300 square metres and $1,863.82 above that. Garages, porches and similar structures cost $214.79. The fee is non-refundable.

Which review stream does a Toronto fourplex go to?

The House stream covers a detached house, a semi-detached house or a row house with no more than two units, plus garden and laneway suites. A building within Part 9 of the Ontario Building Code that is not a house goes to the Small Building stream, reviewed within 15 business days. A building within Part 3, the Code's part for larger buildings, goes to the Large and Complex stream.

What drawings does a Toronto multiplex conversion permit need?

The City's multiplex conversion guide, modified July 14, 2026, asks for a site plan tied to a current survey with a zoning summary, fully dimensioned floor plans for each level showing existing and proposed uses, smoke and carbon monoxide alarms and plumbing fixtures, cross sections with floor, wall and roof assemblies and footing details, and construction details. All drawings and forms are submitted as PDF files.

What forms go with a Toronto multiplex permit application?

The conversion guide lists the Application to Construct or Demolish, the Schedule 1 Designer Information form, the Rental Renovation Licence Screening Form, and for a duplex the Assumption of Responsibility for Engineering Content Form. Exterior work needs a Municipal Road Damage Deposit, additions of 100 square metres or more need a Residential Infill Public Declaration Notice, and work near trees needs a Tree Declaration Form.

What are Toronto's pre-approved multiplex plans?

They are free building plans for four-unit and six-unit multiplexes that the City had prepared by LGA Architectural Partners, in narrow and wide versions with electric, gas or hybrid heating. The City's page, modified November 3, 2026, says they meet the Building Code and the zoning rules for the building itself. You still apply for a permit, and the placement on the lot is reviewed for each site.

Do I still need a designer if I use Toronto's pre-approved multiplex plans?

Yes. The City's page says a qualified design professional must review, take responsibility for and finish the site-specific parts, in signed and sealed letters for the architecture, the structure and the mechanical systems. The structural letter confirms soil bearing capacity, neighbouring footing depths and shoring. Any change to the plan, including HVAC or plumbing, ends its pre-approved status and sends it through the regular process.

What happens when a Toronto examiner sends a notice on my permit?

The City's plan review page, modified October 14, 2026, says the examiner issues a notice explaining why the project does not comply or what information is missing. You upload revised drawings as one PDF through the File Submission Hub, with revision bubbles marking changes, and send only the changed pages. Only one drawing submission is accepted at a time. Supporting documents go to the examiner by email.

Which inspections does a Toronto multiplex need?

The City's schedule for Part 9 buildings lists footings before concrete is poured, foundations, structural framing with plumbing and HVAC rough-in, fire separations before finishes, insulation and vapour barrier, fireplaces and gas appliances, life safety systems, occupancy, and final interior and exterior inspections. Plumbing and HVAC have their own inspections. Inspections take place within two business days of the date you request.

Can people move into a Toronto multiplex before the permit is closed?

Only after the building meets the occupancy rules in Division C, Subsection 1.3.3 of the Ontario Building Code. The City's inspections page, modified November 29, 2024, says an Authority to Occupy application must be submitted before anyone occupies part of an unfinished building. The owner must still book a final inspection when the project is finished to close the permit.

Can a professional engineer's seal speed up a Toronto house permit?

Yes, for houses. The City's review streams page says that, as expanded on July 14, 2025, where drawings for a new house or a material alteration to a house bear a professional engineer's seal, Toronto Building carries out an expedited review and relies on the seal for the matters it covers. The engineer confirms those matters on the Assumption of Responsibility for Engineering Content Form.

Sources

  1. Building Permit Review Streams. City of Toronto, Toronto Building. Modified June 26, 2026. Accessed November 17, 2026.
  2. Zoning Applicable Law Certificate. City of Toronto, Toronto Building. Modified October 15, 2026. Accessed November 17, 2026.
  3. Multiplex Conversion: building permit application guide. City of Toronto, Toronto Building. Modified July 14, 2026. Accessed November 17, 2026.
  4. Pre-Approved Multiplex Building Plans. City of Toronto, Toronto Building. Modified November 3, 2026. Accessed November 17, 2026.
  5. Plan Review Process. City of Toronto, Toronto Building. Modified October 14, 2026. Accessed November 17, 2026.
  6. About Building Inspections: Legislated Mandatory Inspections. City of Toronto, Toronto Building. Modified November 29, 2024. Accessed November 17, 2026.
  7. When to Call for Inspection of Small Buildings. City of Toronto, Toronto Building. Modified November 29, 2024. Accessed November 17, 2026.

Planning and development potential is property-specific and subject to zoning, approvals, site conditions, municipal review and other due diligence. This guide gives general information. For legal, tax or financial advice, ask your own lawyer and accountant.

More in For Developers

Talk About Your Property

Bring the lot, the address or the question. I review the zoning and the numbers with you.

Get in touch