Trees, ravines and conservation rules on a Toronto infill lot: protection zones, permits and the TRCA
This guide is for small builders and owners who plan a multiplex, a suite or an addition on a Toronto lot with trees, or near a ravine or creek. It gives the City's minimum tree protection zone for each trunk size, explains when an as-of-right project still needs a tree permit, lists what a permit application holds, covers boundary and neighbour trees, the Distinctive Tree category and ravine fees that started on September 1, 2026, and explains when the Toronto and Region Conservation Authority must issue a permit before the City can. Every fact comes from a City of Toronto or TRCA page read on November 17, 2026.
Written by Anthony Palleschi · Updated November 17, 2026 · 10 min read
Key takeaways
- A tree protection zone is the area around a tree that must be protected during construction. For a private or street tree of 30 to 40 centimetres it is at least 2.4 metres, rising to 6.0 metres at 91 to 100 centimetres.
- In a ravine or natural area, the protection zone doubles, or reaches the dripline, whichever is greater.
- An as-of-right project that affects a protected tree still needs a permit, and the City may ask for a changed design.
- The City says a laneway or garden suite should not result in the removal of a healthy protected tree, and it may refuse the permit.
- Since September 1, 2026, trees over 61 centimetres on private land and in ravines can be named Distinctive Trees, and ravine permits have application fees.
- Land in or near valleys, watercourses, wetlands and the Lake Ontario shoreline needs a TRCA permit under Ontario Regulation 41/24 before a City building permit.
Why trees decide what fits on a lot
A mature tree in the back yard can set the depth of a multiplex, the position of a garden suite and the route for the excavator. On a Toronto infill lot, the tree rules come from three places: the City's Tree Protection By-law (Municipal Code Chapter 813), its Ravine and Natural Feature Protection By-law (Chapter 658), and, near creeks and valleys, the Toronto and Region Conservation Authority. All three can stop or change a design that the zoning allows.
I am Anthony Palleschi, a real estate sales representative with Weiss Realty Ltd., Brokerage. The guide to screening a lot covers the first checks: which trees are protected, how to measure a trunk, and how to find the ravine map. This guide goes further, into the protection zones, the permit, the 2026 by-law changes and the conservation authority.
The protection zone around each tree
A tree protection zone is the area around a tree that must be protected during construction to keep the tree healthy. The City's When to Apply page, modified January 29, 2026, sets the minimum size by the trunk's diameter, measured 1.4 metres above the ground:
| Trunk diameter | Private tree | City street tree | Tree in a ravine or natural area |
|---|---|---|---|
| Less than 10 cm | Not protected by size | 1.2 m | 1.2 m or the dripline |
| 10 to 29 cm | Not protected by size | 1.8 m | 3.6 m or the dripline |
| 30 to 40 cm | 2.4 m | 2.4 m | 4.8 m or the dripline |
| 41 to 50 cm | 3.0 m | 3.0 m | 6.0 m or the dripline |
| 51 to 60 cm | 3.6 m | 3.6 m | 7.2 m or the dripline |
| 61 to 70 cm | 4.2 m | 4.2 m | 8.4 m or the dripline |
| 71 to 80 cm | 4.8 m | 4.8 m | 9.6 m or the dripline |
| 81 to 90 cm | 5.4 m | 5.4 m | 10.8 m or the dripline |
| 91 to 100 cm | 6.0 m | 6.0 m | 12 m or the dripline |
| More than 100 cm | 6 cm per cm of trunk | 6 cm per cm of trunk | 12 cm per cm of trunk |
The dripline is the area under the outermost branch tips. In a ravine or natural area, the zone is the table figure or the dripline, whichever is greater.
The page says that if any work on site, including access for machines or storage of materials, will affect a protected tree's zone, you must apply for a permit to injure or remove the tree. If the work will not affect any zone, you still protect the nearby trees and complete a Tree Protection Plan with an arborist. The City recommends hiring an arborist to assess the site and measure the zones before the design is fixed.
The page lists the activities that can injure a tree. They include building, demolishing or changing structures, driveways and walkways; digging, trenching, scraping or changing the ground level; storing materials, soil or waste; driving machines or walking over roots; washing out concrete or discharging pool water; and cutting or crushing roots, trunks or branches. For a builder, the practical point is that the staging area and the access route count, as well as the building.
As-of-right projects still need a tree permit
A multiplex or a garden suite that meets the zoning needs no Committee of Adjustment hearing. A tree permit is a separate approval. The City's page says that if an as-of-right project affects a protected tree, you must still apply for a permit to injure or remove it. The City may ask you to revise the design to protect the tree, and if a permit is issued it comes with conditions. Compensation planting is sometimes accepted as cash in lieu.
The page lists work the City does not consider as-of-right construction for this purpose: pools, landscape features, accessory structures such as sheds, gazebos and cabanas, standalone garages, and basements that extend beyond the building's above-ground footprint.
For laneway and garden suites, the City is direct. Its page says a suite should not result in the removal of a healthy protected tree, and that where a design would injure or remove one, the City may refuse the permit under Municipal Code Chapters 608, 658 and 813 and the Official Plan. It advises owners to talk to City staff early about designing the suite around the tree. The garden suites guide covers the suite rules.
The Committee of Adjustment also hears about trees. When you apply for a minor variance or a consent to sever, City staff review the plans for their effect on protected trees and may comment to the Committee. If the variance is approved and the plan still affects a protected tree, you still need the tree permit.
What the permit application holds
The City's How to Apply page lists the documents for an application to remove a tree for construction:
- The application fee, by certified cheque or money order. Current fees are on the application form.
- An arborist report on the tree's location, species, size, condition, structure, disease, pests and health, with the proposed work and protection measures.
- A landscape and replanting plan, with the location, species and size of the replacement tree: at least 50 millimetres in trunk caliper for a deciduous tree, or 1.75 to 2.5 metres tall for a coniferous tree, planted typically in the next spring or fall.
- Colour photos of the whole tree and of any areas of concern.
- A scale site plan showing existing and proposed structures and driveways, every tree of 30 centimetres or more on the property and on neighbouring lots within 6 metres, numbered to match the arborist report, with each protection zone and the hoarding drawn to scale.
- Scale elevations showing the depth and type of excavation for footings, piers or basements.
- Where the lot is in a ravine protection area, a site plan showing the ravine line.
An application to injure a tree, meaning to work inside its zone while keeping it, needs a Tree Protection Plan in place of the replanting plan, and may need floor plans, a basement plan and foundation details near the zone. The page says incomplete applications will not be processed, and that applying does not guarantee a permit.
The building permit side has its own form. The City's multiplex conversion guide asks for a Tree Declaration Form on any project that could damage private or City trees. The building permits guide covers the rest of that application.
Trees on the property line and next door
The City's When to Apply page defines two cases that come up on narrow lots:
- A boundary tree has part of its trunk growing across one or more property lines. It is owned by all the owners. Any of them may apply for a permit, but the others must consent.
- A neighbour tree has its trunk fully on one lot, while its crown or roots reach the next. The owner of the affected lot may apply for a permit.
The page adds that a permit does not decide who owns a tree and does not allow anyone to enter a neighbour's land or remove a tree owned by someone else without consent. Civil disputes are left to the owners. On a lot where a neighbour's large tree sits near the shared line, its protection zone can reach into the building area, so its owner's view matters before the design is fixed.
Ravines and natural features
Every ravine, forest, park, golf course and other natural feature on the City's Ravine and Natural Feature Protection map is protected. Inside the protected area, the When to Apply page says a permit is needed to harm or remove any tree regardless of size, to change the ground by digging or adding soil on slopes, to place fill or waste, or to build or replace structures or retaining walls.
If the project needs site plan approval or a building permit, the ravine permit is reviewed with it. The How to Apply page says a ravine permit is issued after site plan approval, or on condition that the building permit issues. The application needs the zoning notice for the construction, a survey showing the limits of the protected area and a site plan.
From September 1, 2026, the City charges application fees for ravine permits. The City's Tree Bylaw Review page lists them:
| Application | Fee |
|---|---|
| Ravine tree, construction | $262.72 per tree |
| Ravine boundary or neighbour tree, construction | $549.08 per tree |
| Ravine tree, non-construction | $87.57 per tree |
| Ravine boundary or neighbour tree, non-construction | $183.03 per tree |
| Alteration of grade, no trees | $632.51 per application |
The How to Apply page says the fees are non-refundable and updated each year, with exemptions for voluntary stewardship and some eligible projects.
The 2026 changes to the tree by-laws
The Tree Bylaw Review page lists the changes Council directed through Item 2026.IE27.8, several of which took effect on September 1, 2026:
- A new Distinctive Tree category for large, healthy trees over 61 centimetres in diameter on private property and in ravines. City staff identify them, and they must be considered through the tree permit when an application is made to injure or remove one.
- Trees planted through enforcement or as a condition of a development approval are protected at any size.
- A stump of 40 centimetres or more can be used to measure a removed tree whose trunk is gone.
- Replacement planting after a contravention moves to a ratio based on the tree's diameter, starting at 5 to 1 and rising for larger trees.
- Quarterly reports of tree permit and contravention outcomes on the City's Open Data portal.
Council has also endorsed lowering the protected size for private trees from 30 to 20 centimetres, pending further analysis and an implementation plan to be reported to the Infrastructure and Environment Committee in 2027. The page links the changes to the City's goal of 40 percent tree canopy cover by 2050.
A separate proposal is still open. The City's Growing Space for Trees page, modified February 6, 2026, describes proposed Official Plan and zoning changes on soft landscaping, setbacks and "iceberg homes", houses with large basements that reach below ground beyond the building above. The page says staff reported to Council in February 2026, and that Council asked staff to report back on issues related to multiplexes, swimming pools and the below-ground footprint of small apartment buildings on Major Streets.
The conservation authority
The City's When to Apply page notes that the Toronto and Region Conservation Authority regulates development in or near watercourses, river and stream valleys, the Lake Ontario shoreline and wetlands. The TRCA's permit page says it issues permits under the Conservation Authorities Act and Ontario Regulation 41/24, and that a TRCA permit is required before a building permit from the municipality.
The TRCA recommends checking first whether the site is regulated, with its Regulated Area Search tool, and strongly encourages a meeting before applying. Its page says a planner confirms receipt within two business days, completeness is decided within 21 days, pre-application meetings are generally held within 2 to 15 business days of a request, and permits are issued for two years. The review fee is confirmed by the planner after the application is submitted.
What this means for a builder and an owner
For a builder, trees belong at the start of due diligence, before the purchase price is fixed. Ask for a survey that shows the trees, have an arborist measure every protected tree on the lot and within 6 metres of it, draw the protection zones on the site plan, and check the ravine map and the TRCA search. A design that keeps every zone clear avoids a permit to injure or remove. A design that cannot may still work, with a permit, conditions and replanting, or it may need to change. The guide to testing the numbers shows where a smaller building or a delay enters the pro forma.
For an owner selling to a builder, a large tree in the back yard is part of what the builder prices. A family buyer sees shade and privacy. A builder sees a protection zone that may limit the building's depth or rule out a garden suite. The guide to how builders price land explains how those limits turn into an offer.
Questions to ask about trees on a lot
- How many trees of 30 centimetres or more stand on the lot, and on neighbouring lots within 6 metres?
- How far does each protection zone reach, and does it cross the building, the access route or the staging area?
- Is any tree on the property line, and will the neighbour consent?
- Is any tree over 61 centimetres, where the Distinctive Tree rules may apply?
- Is the lot inside the ravine protection area or a TRCA regulated area?
- Would a garden suite, a basement or a pool need a tree to come down?
If you want a lot reviewed for these limits before you make an offer, the contact page reaches me directly.
Planning and development potential is property-specific and subject to zoning, approvals, site conditions, municipal review and other due diligence. This guide is illustrative and does not guarantee similar permissions or outcomes for another property.
Frequently asked questions
What is a tree protection zone in Toronto?
A tree protection zone is the area around a tree that must be protected during construction to keep the tree healthy. The City's When to Apply page, modified January 29, 2026, says that if any work on site, including access or storage, will affect a protected tree's zone, you must apply for a permit to injure or remove the tree. If it will not, you still protect nearby trees under a plan prepared with an arborist.
How big is the tree protection zone for a 50 centimetre tree in Toronto?
The City's table sets a minimum of 3.0 metres for a private tree or a City street tree with a trunk of 41 to 50 centimetres measured 1.4 metres above the ground. For the same tree in a ravine or natural area, the minimum is 6.0 metres or the dripline, the area under the outermost branch tips, whichever is greater. Above 100 centimetres the zone grows by 6 centimetres for each centimetre of trunk.
Does an as-of-right multiplex in Toronto need a tree permit?
It does if it will injure or remove a protected tree. The City's When to Apply page says an as-of-right project that affects a protected tree still needs a permit, the City may ask for a revised design to protect the tree, and permit conditions apply if a permit is issued. The City does not treat pools, sheds, standalone garages or basements beyond the building's above-ground footprint as as-of-right construction.
Can a Toronto garden suite remove a protected tree?
The City says laneway and garden suites should not result in the removal of a healthy protected tree. Where a design would injure or remove one, the City may refuse the tree permit under Municipal Code Chapters 608, 658 and 813 and the Official Plan. Its page advises owners to contact City staff early to discuss how a suite can be designed around a healthy tree.
What does a Toronto tree removal permit application need for construction?
The City's How to Apply page lists the fee, an arborist report on the tree's species, size, condition and health, a landscape and replanting plan, colour photos, a scale site plan and elevations. The site plan shows every tree of 30 centimetres or more on the property and on neighbouring lots within 6 metres, numbered to match the report, with each protection zone and its hoarding drawn to scale.
How big must a replacement tree be in Toronto?
The City's How to Apply page says the landscape and replanting plan must show a replacement tree of at least 50 millimetres in trunk caliper for a deciduous tree, or 1.75 to 2.5 metres in height for a coniferous tree. It also asks for the planting location, the species and the planting season, which is typically the next spring or fall. The City says compensation planting is sometimes accepted as cash in lieu.
Who can apply to remove a tree on the property line in Toronto?
A tree whose trunk grows across a property line is a boundary tree owned by both owners. The City says either owner may apply, but the other owner must consent. A neighbour tree has its trunk fully on one lot while its crown or roots reach the next one, and the owner of the affected lot may apply. A permit does not allow anyone to enter a neighbour's land or remove a tree they do not own.
What is a Distinctive Tree in Toronto?
It is a category the City added on September 1, 2026 for large, healthy trees on private property and in ravines that are more than 61 centimetres in diameter. The City's Tree Bylaw Review page says City staff identify Distinctive Trees, and that they must be considered through the tree permit process when an application is made to injure or remove them.
How much is a Toronto ravine permit for a construction project?
From September 1, 2026, the City charges $262.72 per tree for a ravine tree permit tied to construction, and $549.08 per tree for a ravine boundary or neighbour tree tied to construction. Non-construction permits are $87.57 and $183.03 per tree. Altering the grade with no trees involved is $632.51 per application. The City says the fees are non-refundable and updated each year.
Does the Committee of Adjustment look at trees in Toronto?
Yes. The City's When to Apply page says that when you apply for a minor variance or a consent to sever, City staff review the plans for their effect on protected trees, ravines and natural features and may comment to the Committee before its meeting. If the Committee approves the variance and the plan affects a protected tree, you still need a tree permit, and may be asked to revise the design or plant compensation trees.
Do I need a TRCA permit before a Toronto building permit?
Yes, if the project is in a regulated area. The Toronto and Region Conservation Authority's permit page says it regulates development in or near hazardous lands, wetlands and river or stream valleys, and work that interferes with a watercourse, under Ontario Regulation 41/24, and that its permit is needed before a municipal building permit. It checks completeness within 21 days, and permits are issued for two years.
Will Toronto protect smaller private trees in the future?
Council has endorsed lowering the minimum protected size for private trees from 30 centimetres to 20 centimetres, according to the City's Tree Bylaw Review page. The page says this waits on further analysis and an implementation plan, to be reported to the Infrastructure and Environment Committee in 2027. Until a by-law change takes effect, the 30 centimetre threshold applies to private trees.
Sources
- When to Apply for a Tree or Ravine Permit. City of Toronto, Urban Forestry. Modified January 29, 2026. Accessed November 17, 2026.
- How to Apply for a Tree or Ravine Permit. City of Toronto, Urban Forestry. No modified date shown. Accessed November 17, 2026.
- Tree Bylaw Review. City of Toronto. Changes in effect September 1, 2026. Accessed November 17, 2026.
- Growing Space for Trees. City of Toronto, City Planning. Modified February 6, 2026. Accessed November 17, 2026.
- Apply for a Permit. Toronto and Region Conservation Authority. No date shown. Accessed November 17, 2026.
- Multiplex Conversion: building permit application guide. City of Toronto, Toronto Building. Modified July 14, 2026. Accessed November 17, 2026.
Planning and development potential is property-specific and subject to zoning, approvals, site conditions, municipal review and other due diligence. This guide gives general information. For legal, tax or financial advice, ask your own lawyer and accountant.