Toronto Boulevard and Right-of-Way Rules: What a Multiplex Needs from the City Street

Written by · December 2, 2026 · 8 min read

A sunny Toronto side street with a mature boulevard tree in front of a new multiplex, a new driveway cut to one side of it

The strip of land between your fence and the curb is not yours. It is the City's road allowance, and Toronto has a separate set of rules for what can happen on it. For a new Toronto multiplex, every connection between the building and the street (driveway, water, sanitary, hydro, gas) touches the road allowance and needs its own permit. The permits are usually small on paper. The works behind them are where the real costs sit.

I'm Anthony Palleschi, a real estate sales representative in Toronto, working with owners and builders on sites where the boulevard conditions change the lot value. This post sets out what the right-of-way rules cover, where each permit sits, and what an owner can check before a listing.

What the boulevard is

The road allowance, or ROW, is the strip of land from the centre line of the road to the private property line. On a typical Toronto residential street, the ROW is 20 metres (66 feet) wide. The parts of it are:

Typical layout of a 20-metre Toronto residential road allowance
ElementTypical widthWho owns it
Travelled road surface7 to 10 mCity of Toronto
Parking lane, each side2 to 2.5 mCity of Toronto
Curb150 mmCity of Toronto
Boulevard (grass, tree)1 to 3 mCity of Toronto
Sidewalk1.5 to 2.0 mCity of Toronto
Boulevard (grass, between sidewalk and property line)0.5 to 2 mCity of Toronto
Private property lineLineOwner

The boulevard, both the inside strip and the outside strip, is City land. The sidewalk is City land. The street trees are City trees. Any excavation, any paving, any new planting, any utility line that crosses that land needs the City's permission.

The right-of-way permits a multiplex needs

Five right-of-way permits show up on most Toronto multiplex projects.

1. Driveway curb cut permit. Issued by Transportation Services. Covers a new driveway cut, a widening, or a change of location. Fee $500 to $1,500. Review time 4 to 8 weeks. The permit sets out the driveway width (set by the zoning by-law), the apron design (how the driveway meets the curb), and any sidewalk reconstruction.

2. Water service permit. Issued by Toronto Water. Covers the connection from the water main (in the middle of the road) to the property line. Fee $500 to $2,000. Work cost $8,000 to $25,000 for a new or upsized service. The permit includes the road cut, the saddle on the main, the new service line, and the restoration of the road and sidewalk.

3. Sanitary connection permit. Issued by Toronto Water. Covers the connection from the sanitary main to the property line. Similar fee and work cost structure to the water service. On a multiplex, the existing sanitary connection is sometimes reusable and sometimes needs replacement.

4. Street occupancy permit for construction. Issued by Transportation Services. Covers the right to place a construction fence, a container, a staging area, or a hoist on the road allowance during construction. Fee $200 to $800 per month, depending on the length of occupancy and the width used.

5. Boulevard works or encroachment agreement. Issued by Transportation Services. Covers any new encroachment (a stair, a bay window), or any private use of the boulevard (landscaping, a planter). Annual fee for an encroachment agreement is $100 to $500. A new encroachment agreement is registered on title.

For a lot facing a major street, see my post on Toronto major streets zoning. Major streets often have additional constraints on curb cuts and setbacks.

Boulevard trees: a separate review

A boulevard tree in front of the lot is protected under Chapter 658 of the Toronto Municipal Code. Unlike Chapter 813 for private trees, the boulevard tree by-law has no diameter threshold. A tree the City planted last week is as protected as a 100-year-old oak.

For a new multiplex, any of the following triggers an Urban Forestry review:

  • A new driveway cut within 3 metres of the trunk.
  • A new water service trench under the root zone.
  • A new sanitary connection trench.
  • A new sidewalk reconstruction in front of the tree.
  • Any grading of the boulevard.
  • A construction fence or staging area around the tree.

The review requires a Tree Protection Plan showing the Tree Protection Zone (TPZ), the construction fencing, and any root-sensitive work. The usual TPZ ratio of 10 cm radius per cm of trunk diameter applies. See my private tree by-law post for how the TPZ works.

Urban Forestry rarely approves the removal of a healthy boulevard tree for a private project. A new driveway that would require removal of a boulevard tree is almost always redesigned. On a narrow lot with a mature tree directly in front, the driveway may need to move to the opposite side of the lot or be eliminated.

Curb cuts on a major street

On a residential street, a curb cut is usually possible if there is no boulevard tree or utility conflict. On a major street, the rules are tighter. Transportation Services often restricts or prohibits new curb cuts on a major street to protect through-traffic capacity and pedestrian safety.

Three common major-street rules:

  • No new curb cuts where the lot has frontage on an alternative street (a side street or a lane).
  • Curb cut width limited to 2.5 to 3.5 metres, less than the typical 4.5 to 6.0 metres on a residential street.
  • Curb cut spacing of at least 20 to 30 metres between driveways.

For a multiplex on a major street with a lane at the rear, the parking is normally served from the lane. The front remains sidewalk and boulevard, with no curb cut.

The water service upsize

A single-family house in Toronto typically has a 15 mm (half-inch) copper water service. A multiplex of four to ten units typically needs a 19 mm (three-quarter-inch) or 25 mm (one-inch) service. The upsize means:

  1. Closing the road in front of the lot for a day to two days.
  2. Digging a trench from the water main to the property line.
  3. Installing a new saddle on the main and a new service line.
  4. Restoring the road, sidewalk and boulevard to City standard.
  5. Installing a new water meter in the building.

Toronto Water does the main-to-property-line work. The owner's plumber does the property-line-to-building work. The combined cost is $10,000 to $25,000 for a typical residential multiplex, plus a connection charge that varies by service size.

A lot that was previously served by a 15 mm line and is now a fourplex needs the upsize before Toronto Water signs off on the building permit. See my permit timeline post for how the water service review fits with the other permit reviews.

Encroachments and the setback

An encroachment is any part of a building that extends past the private property line onto the City's road allowance. Common encroachments:

  • Front stairs. A step or a landing that reaches the sidewalk.
  • Porch. A roof overhang or a porch slab that extends past the setback line.
  • Bay window. A projecting bay that extends past the setback line at the upper levels.
  • Below-grade features. A window well or a basement light well.

An encroachment of 150 to 300 millimetres into the City road allowance is often approved under a standard encroachment agreement. A larger encroachment is reviewed on its own merits. The agreement is registered on title and the owner pays an annual fee.

A building designed to fit entirely within the private property line does not need an encroachment agreement. For a small lot where the as-of-right setback is only 4.5 to 6 metres from the lot line, the architect often tries to keep the stairs and the bay window inside the property line so an agreement is not needed.

What an owner can do before listing

Three steps give a buyer a clear picture of the right-of-way conditions.

  • Call Transportation Services for a curb cut opinion. A short call confirms whether a new curb cut is possible on the street, and whether the width would allow it. No formal application is needed.
  • Call Toronto Water for the water service size. A free information request confirms the existing service size, the main size, and whether the local main has capacity for an upsize.
  • Walk the boulevard. Note every tree in front of the lot, every utility pole, every transformer pad and every fire hydrant. Those are fixed constraints on where a driveway can go.

For the broader pricing framework, see how builders price land in Toronto. For other servicing conditions, see the grading and drainage post and the tree by-law post.

Common mistakes

  • Assuming a curb cut is available. A listing that shows a new driveway in the renders does not promise the driveway can be built.
  • Forgetting the boulevard tree in the way of the trench. The water service trench runs under the tree's root zone. Urban Forestry has a view on that.
  • Underestimating the water service cost. A $20,000 service upsize is not unusual on an older block.
  • Encroaching without an agreement. A new porch that sits 400 millimetres over the property line is a problem the City finds at the final inspection.
  • Treating the sidewalk as private. A damaged sidewalk from construction is a Transportation Services restoration order.

Questions to ask about your lot's right of way

  • Is a new driveway cut permitted on this street?
  • Where is the nearest boulevard tree, and what is its trunk diameter?
  • What is the existing water service size, and does the main have capacity for an upsize?
  • Are there any existing encroachments on title?
  • Does the lot have lane access at the rear?

If you want to walk through what the right-of-way conditions mean for a specific lot, see how I work with sellers and builders, or reach me through the contact page.

Planning and development potential is property-specific and subject to zoning, approvals, site conditions, municipal review and other due diligence.

Sources

All pages opened on November 25, 2026 (PT).

Frequently asked questions

What is the Toronto boulevard?

The boulevard, or road allowance, is the strip of land between the back of the sidewalk and the private property line. In many Toronto streets it is 1 to 3 metres wide. The City owns it, including the grass, the street trees, and in most cases the sidewalk. Any work on the boulevard needs a right-of-way permit from Transportation Services. Private landscaping on the boulevard is allowed in some cases under a boulevard occupancy agreement.

Do I need a permit to add a driveway in Toronto?

Yes. A new driveway cut, or a widening of an existing one, needs a curb cut permit from Transportation Services. The curb cut is reviewed for traffic safety, sidewalk continuity, boulevard tree protection, and the width of the driveway. Most residential curb cuts take 4 to 8 weeks from application to permit, with the fee in the $500 to $1,500 range.

Can I cut a curb to add parking for a multiplex in Toronto?

A new curb cut is allowed on a residential lot when the lot has frontage on a street where a curb cut is permitted. On a major street, curb cuts are often restricted or prohibited. On a residential street, a curb cut is usually permitted if it does not conflict with a boulevard tree, a bus stop, a fire hydrant, a utility pole or a transit shelter. The driveway is limited to a maximum width set by the zoning by-law.

What is a right-of-way permit in Toronto?

A right-of-way permit is Transportation Services' approval for work on the City's road allowance (the boulevard, the sidewalk and the road). For a new multiplex, the common right-of-way permits are the driveway curb cut, the water service connection, the sanitary connection, the street occupancy for construction, and the boulevard works for a utility hook-up.

Do I need a permit for a boulevard tree near my new build?

A boulevard tree is protected under Toronto Municipal Code Chapter 658, with no size threshold. Any work near the tree (excavation, driveway construction, utility trenching, grading, root cutting) needs Urban Forestry's approval. For a new driveway or a new utility service that comes within 3 metres of the trunk, a Tree Protection Plan is required, along with an Urban Forestry inspection during construction.

What is a boulevard occupancy agreement in Toronto?

A boulevard occupancy agreement is a licence from Transportation Services that lets a property owner use the City's boulevard for a specific purpose, usually landscaping, a planter, a small fence or a bicycle rack. The agreement is at the City's discretion, pays an annual fee, and can be revoked by the City. The agreement does not transfer ownership of the boulevard to the private owner.

How much does a new water service cost in Toronto?

A new or upsized water service from the water main to the property line costs $8,000 to $25,000 for a residential multiplex. The cost depends on the size of the service (15 mm, 19 mm, 25 mm or larger), the depth of the water main, the distance from the main to the lot, and whether the work requires a road cut. Toronto Water does the connection to the main, and the owner's contractor digs the trench on the private side.

Do I need an encroachment agreement for a new building?

A new building that encroaches onto the City's road allowance (a stair, a porch, a bay window) needs an encroachment agreement with Transportation Services. The agreement is registered on title, pays an annual fee, and sets out the owner's responsibility to remove the encroachment if the City needs the land. A small encroachment of 150 to 300 millimetres is often routine; a larger one is reviewed on its own merits.