Toronto takes storm water seriously. The City's Wet Weather Flow Management Guidelines and Chapter 681 of the Toronto Municipal Code require every new building to manage its storm water on its own lot, so the water that falls on the roof and the driveway does not flow to the neighbour and does not overload the City sewer. For a multiplex, the storm water management plan is a line in the proforma that is either small (a few hundred dollars of works) or large (a $20,000 to $30,000 cistern or infiltration bed) depending on the lot.
I'm Anthony Palleschi, a real estate sales representative in Toronto, working with owners and builders on sites where the servicing conditions change the value. This post sets out how the grading and drainage rules work, what the storm water plan has to show, and where the costs sit.
The rule in one line
A new building in Toronto has to keep its storm water on its own lot, and the surface grades have to slope water away from every building and away from adjoining lots. The target is the pre-development runoff rate. The new lot cannot send more water to the City sewer than the old one did, and cannot send any additional water onto the neighbours.
The rule has three parts:
- Flow rate control. The post-development peak flow rate from the lot to the sewer matches the pre-development rate for a defined design storm.
- Volume control. The first 5 to 35 millimetres of rainfall on the new impervious area is captured and either infiltrated or stored for slow release.
- Surface grading. The finished grades slope water away from every building on the lot, and the pattern does not direct water onto adjoining lots in a way that worsens their drainage.
For most multiplexes, the first two parts are handled by a single system: a flow control device, a cistern, an infiltration bed, or a combination. The third part is handled by the site plan.
What counts as impervious
Impervious surface is any surface that does not let water soak in. For a multiplex lot, the main contributors are:
| Feature | Impervious? | Rough area on a 40 by 120 ft lot |
|---|---|---|
| Roof of the main building | Yes | 140 to 200 m² |
| Driveway and parking pad | Yes | 35 to 60 m² |
| Laneway suite roof, if present | Yes | 30 to 50 m² |
| Walkways and patios | Yes, unless permeable | 15 to 30 m² |
| Landscaped yard | No | varies |
| Permeable paver driveway | Partially | counted at 50 percent |
A traditional single-family house on a 40 by 120 lot has about 90 to 120 m² of impervious surface. A new fourplex on the same lot with a laneway suite can have 230 to 320 m². The increase in impervious area is where most of the storm water work comes from.
The three solutions in use
Most Toronto multiplex storm water plans use one of three solutions, sized by the volume of water the new impervious area generates for the design storm.
Solution 1: Flow control device. A small plastic device, usually about the size of a shoebox, is installed in the downspout line or the sanitary connection. It restricts the rate of water leaving the lot to a set figure. The device costs $500 to $1,500, and the installation is routine. Suitable for a lot with modest impervious increase and good surface drainage.
Solution 2: Infiltration bed. A gravel bed, usually 3 to 5 cubic metres, sits under the back yard or the parking pad. Water from the downspouts runs into the bed, where it soaks into the ground. The bed is sized to hold the first 25 to 35 millimetres of rainfall on the new impervious surfaces. Cost is $8,000 to $18,000, including the geotechnical check and the perforated piping. Suitable for a lot with sandy or well-drained native soil.
Solution 3: Cistern. A sealed tank, usually 3,000 to 5,000 litres, sits in the basement or under the back yard. The tank captures roof runoff and releases it slowly to the sanitary or storm sewer, or runs it to an irrigation system. Cost is $15,000 to $30,000, depending on the size. Suitable for a lot with clay soil or a high water table, where infiltration does not work.
A larger project may use a combination (a cistern plus an infiltration bed, or a flow control device plus a green roof). The civil engineer picks the combination based on the lot's soil, the design storm, and the available space.
Grading between lots
The finished grade of a new multiplex lot has to:
- Slope away from the building at a minimum of 2 percent for the first 2 metres (a drop of 4 centimetres per metre).
- Slope across the lot at a minimum of 1 percent to a defined drainage outlet.
- Not direct water onto an adjoining lot in a way that increases the volume or changes the pattern from the pre-development condition.
- Not exceed a 3:1 slope anywhere on the lot (one vertical for three horizontal), unless a retaining wall is designed.
A lot that is below the neighbouring grade needs a retaining wall. The wall is a structural element with its own set of rules under the Ontario Building Code. See the Toronto Height Overlay post for how the building height is measured from the average grade, which is affected by the retaining wall.
Flood-prone areas and TRCA
A lot inside a Toronto and Region Conservation Authority (TRCA) regulated area goes through a TRCA permit as well as the City review. TRCA regulates lots in flood plains, on erosion hazards, in wetland areas and along watercourses. The TRCA map is published at trca.ca and should be checked on every lot before an offer.
A TRCA permit for a residential project typically takes 6 to 10 weeks. It is an added line on the timeline for the small share of Toronto lots that touch a regulated area, usually along the Don, Humber or Rouge river valleys, or near the Lake Ontario shoreline.
How the plan is reviewed
The storm water management plan is reviewed by Toronto Water as part of the building permit. The plan is prepared by a civil or servicing engineer, signed and sealed, and submitted with the building permit application. See my permit timeline post for how the Toronto Water review fits with the other three reviews.
The review usually produces one round of comments on the first submission. The common comments are:
- The post-development flow rate exceeds the pre-development rate. Resize the flow control or add volume control.
- The infiltration bed sizing does not match the lot's native soil. A geotechnical report is needed.
- The grading plan does not show the neighbours' grades. A topographic survey of the surrounding properties is needed.
- The downspouts discharge too close to the lot line. Route them further in, or add a splash pad.
The comments are usually resolved in a drawing revision and a short response letter, which takes 2 to 4 weeks.
What an owner can do before listing
Three steps give a buyer a clear picture before the offer.
- Order a topographic survey. A $500 to $1,200 survey shows the grades at every corner of the lot and on the surrounding properties. A buyer with a topographic survey can budget the storm water work without a site visit.
- Order a servicing engineer letter. For $300 to $600, a servicing engineer gives a one-page letter stating whether the lot is suitable for infiltration or will need a cistern. The letter is not a storm water management plan, but it tells a buyer which category the lot is in.
- Ask Toronto Water about the sewer capacity. A free information request confirms whether the local sewer has capacity for a multiplex and whether a service upgrade is needed.
For a builder's pricing framework, see how builders price land in Toronto. For other servicing conditions, see the permit timeline post.
Common mistakes
- Treating storm water as an afterthought. A design that is set before the servicing engineer looks at it often needs expensive rework.
- Skipping the topographic survey. The architect's drawings are only as good as the grades underneath them.
- Underestimating the roof area. A green roof, a mansard roof or a stepped-back third storey all have different roof areas, and each affects the storm water target.
- Forgetting the lot across the lane. A lot with a laneway suite sends the laneway roof water somewhere. A design that sheets water onto the lane is a problem.
- Missing a TRCA regulated area. A lot touching a ravine or a flood plain is a different file.
Questions to ask about your lot
- What are the grades at the four corners of the lot?
- Does my lot slope toward the street, the back lane, or the neighbours?
- Is my lot inside a TRCA regulated area?
- Does the local sewer have capacity for a multiplex?
- Would my lot need a flow control device, an infiltration bed or a cistern?
If you want to walk through what the storm water rules mean for a specific lot, see how I work with sellers and builders, or reach me through the contact page.
Planning and development potential is property-specific and subject to zoning, approvals, site conditions, municipal review and other due diligence.
Sources
All pages opened on November 25, 2026 (PT).
- City of Toronto, Toronto Municipal Code Chapter 681, Sewers: the rules on connections to the City sewer and the control of storm water from private lots.
- City of Toronto, Wet Weather Flow Management Guidelines: the storm water targets, the design storms and the control hierarchy.
- City of Toronto, Toronto Water Design Guidelines: the grading tolerances and the service connection standards.
- Toronto and Region Conservation Authority, Living City Policies: the TRCA permit process for regulated areas, flood plains and ravines.
Frequently asked questions
What is Toronto's grading and drainage rule?
Toronto's wet weather flow management guidelines and Chapter 681 of the Toronto Municipal Code require every new building to control the storm water on its own lot. The design has to show that the new roof, driveway and paved areas do not send more water onto the neighbours or into the City sewer than the existing lot did, and the surface grades have to slope water away from the building and away from adjoining lots.
What is a storm water management plan in Toronto?
A storm water management plan, or SWMP, is a drawing and a short report that shows how the new building will manage its storm water. For a multiplex, the SWMP typically shows the roof drainage, the downspout routing, any infiltration or detention measure, the pre-development and post-development flow rates, and the final grades of the lot. The SWMP is reviewed by Toronto Water as part of the building permit.
Does a Toronto fourplex need a cistern?
Not always. A fourplex on a well-drained lot can usually manage storm water with a flow control device at the downspouts and a landscaped swale. A fourplex on a flat or poorly drained lot, or one that adds a lot of impervious surface, often needs a cistern or an infiltration bed sized to the Toronto Water target. The target is set by the lot's impervious area and the pre-development flow rate.
What is the Toronto grading tolerance between lots?
Toronto Water's Design Guidelines require a minimum slope of 2 percent away from the building for the first 2 metres, and a minimum of 1 percent across the lot to the drainage outlet. The new lot's finished grade cannot direct water onto an adjoining lot in a way that increases the volume or changes the pattern from the pre-development condition. Grade changes at a lot line are limited by a retaining wall and drainage design.
Who approves grading in Toronto?
The grading plan for a multiplex is reviewed by Toronto Water and Toronto Building together, as part of the building permit. A larger project of 11 or more units, or a project in a flood-prone area, may also go to the Toronto and Region Conservation Authority. The grading on site is inspected during construction by a building inspector and a Toronto Water inspector.
What happens if my lot drains onto a neighbour?
If the existing lot drains onto a neighbour, the new design has to correct the drainage pattern or match it in a way that does not worsen the situation. If the new lot is built in a way that increases runoff onto the neighbour, the neighbour can file a complaint with the City, which can order corrective work. In some cases a disagreement ends up in a private action under the common law of nuisance.
Does a new multiplex need an infiltration bed?
A multiplex that adds a significant amount of impervious surface, or one on a lot that cannot shed its water fast enough, often needs an infiltration bed or a dry well under the back yard or the parking area. The size of the bed is set by the Toronto Water target, usually to capture the first 25 to 35 millimetres of rainfall on the new impervious area. A cistern is an alternative that can also serve the irrigation system.
What is the cost of a storm water management plan?
A storm water management plan for a Toronto multiplex costs about $3,000 to $8,000, prepared by a civil or servicing engineer. The cost of the physical works depends on the lot and the target: a flow control device costs $500 to $1,500, a cistern system of 3 to 5 cubic metres costs $15,000 to $30,000, and an infiltration bed of the same size costs $8,000 to $18,000.